Projects

100 KLPD ENA/ Ethanol Project

[2013-2024 Karthik Agro Industries PVT]

About

EBP blending program initiated by government of India to blend 20% ethanol with petrol to be achieved by 2025. Incentives provided by government of India to set up new ethanol plant gave the idea to implement this project.

Roles and Responsibilities 

  • Concept to Commissioning.
  • Specification of plant and machineries.
  • Project finalisation with plant suppliers.
  • New boiler installation and commissioning.
  • New turbine installation and commissioning.
  • Utilities:
    • Air compressor
    • Water treatment plants
    • Effluent treatment plants
    • DM plants
    • Cooling towers
  • Flour mil section with grain silos.
  • Liquification plants.
  • Fermentation plants.
  • Distillation plants.
  • MSDH plants.
  • Evaporation plants.
  • DDGS driers.
  • Electrical and instrumentation selection and implementation.
  • Civil design and implementation.
  • Structural design and implementation.
  • Selection of pipes and valves.
  • Project completion and commissioning achieved with desired quality and projected capacity.
  • Liasoning with government authorities such as boiler inspector, electrical inspector, factory inspector, safety inspector and PESO.

65 KLPD RS to Ethanol Project

[2013-2024 Karthik Agro Industries PVT]

About

EBP blending program initiated by government of India to blend 20% ethanol with petrol to be achieved by 2025. Incentives provided by government of India to set up new ethanol plant gave the idea to implement this project.

Roles and Responsibilities

  • Concept to Commissioning.
  • Project Identification and getting EC.
  • Obtaining CFE and CFO from respective PCB.
  • Specification of plant and machineries.
  • Project finalisation with plant suppliers.
  • New boiler installation and commissioning.
  • New turbine installation and commissioning.
  • Utilities:
    • Air compressor
    • Water treatment plants
    • Effluent treatment plants
    • DM plants
    • Cooling towers
  • Flour mil section with grain silos.
  • Liquification plants.
  • Fermentation plants.
  • Distillation plants.
  • MSDH plants.
  • Evaporation plants.
  • DDGS driers.
  • Electrical and instrumentation selection and implementation.
  • Civil design and implementation.
  • Structural design and implementation.
  • Selection of pipes and valves.
  • Project completion and commissioning achieved with desired quality and projected capacity.
  • Liasoning with government authorities such as boiler inspector, electrical inspector, factory inspector, safety inspector and PESO.

Enhancement of existing 65 KLPD ENA plant to 100 KLPD

[2013-2024 Karthik Agro Industries PVT]

About

Increasing the capacity of the existing plant.

Innovation and Achievements

  • Modification in the equipment with negligible investment.
  • Process modification resulted in achieving capacity up-to 100 KLPD with desired quality.
  • Increased boiler capacity from 16 TPH to 18 TPH.
  • Addition of extra cooling tower to de-bottle neck the requirement of cooling water for process application.
  • Conservation of electric power by providing VFD's whereever required.
  • Enhancing efficiency optimum requirement to continue operation of the plant more than 330 days in a year.

Other projects

[1995-2008 Deepak Nitrite | 2011-2013 Vinati Organics LTD]

  • Implementation of chemical projects such as pracumidine, ONA, MCA, OPDA, nitroxylene, ATBS along with required utilities.